Austin Energy EV Charging Rebate: What Property Owners Need to Know
Texas doesn't hand out much money for EV charging. Austin is the exception.
Austin Energy has a Business EV Charger Rebate, and apartment properties qualify.
It's the incentive REVS has used more than any other since we started, and it's the one we point Austin owners to first.

What it pays
Up to $3,000 for each Level 2 station you install.
Up to six stations at one address per year.
The rebate can't be more than half of what you spend on the equipment and the work to install it.
Six stations at $3,000 is up to $18,000 back on one property, though the 50 percent cap means you only reach that if the project runs $36,000 or more.
The clock just reset
Austin Energy runs on a fiscal year that starts in October. You get one application per address per year. That means the year turned over about five weeks ago and every Austin property has a fresh allocation right now.
It's also first come, first served, and the funding is limited. The properties that move early in the year are the ones that get paid.
The part that catches people
Most rebate programs work one way. You apply before you build, they hold the money for you, and then you install knowing it's there.
Austin Energy works the other way around.
You install the stations. You pass your City of Austin inspection. Then you apply, and you have 180 days from the day the stations go live to get your paperwork in.
So, you spend the whole amount up front with no promise the money will still be there. On a first come, first served program, that's a real risk, and it's the single biggest difference between this rebate and most others.
The good news is Austin Energy moves quickly once you submit your application. On our applications we usually hear back with an approval inside two weeks, and often inside a week. That is far faster than most programs, where months is normal.
The small things that get applications rejected
Austin Energy is specific about what the finished job has to look like, and it's easy to miss one piece.
Every charging spot needs a wheel stop or bollard protecting the station.
Every spot needs an "EV Charging Only" sign and a tow away sign.
You must send photos showing the station, the signs, and the barrier.
The hardware has to be new, safety listed, and speak OCPP, which is the open standard most networks use.
Equipment upgrades, and make-ready work on their own don't qualify.
Your City of Austin permit inspection must be closed out before you apply.
None of that is hard. It's just a list, and if one item is missing the application sits.
See below for the perfect submission:

What we do with it
REVS files this one for our customers. We know what Austin Energy wants, we plan the signage and the barriers into the job instead of adding them later, and we handle the application and the photos.
We also build the rebate into the project from the start. Knowing what you'll get back changes what makes sense to install, and it's better to know that before you pick the scope of the job.
Our multifamily EV charging page covers how these projects come together, and our financing page covers the ways to pay for one.
If you own property in Austin
Start with what your building can carry. That sets your real cost, which sets your real rebate, and it's the first thing anyone will ask you.
An EV charging due diligence report gives you that answer before you commit to anything.
If you own or manage apartments in Austin and want to use this year's allocation, contact REVS and we'll take a look at your properties.